Springfield Parkway Stage 2 Contract Awarded as September Works Continue

The construction contract for Stage 2 of the Springfield Parkway duplication has been awarded, while water main works continued around the date previously nominated for the next phase of the major road upgrade.



Ipswich City Council formally awarded Tender 5893 on 27 August, days before the proposed 1 September 2026 commencement date announced in February. The publicly available resolution does not identify the successful contractor or contract amount, with those details contained in a confidential attachment. 

Council had forecast completion of Stage 2 by December 2027.

Night works overlap proposed September start

A council works notice dated 19 August scheduled Stage 2 water main works along Springfield Parkway between Topaz Road and the Springfield Parkway roundabout from 30 August to 4 September, subject to weather and site conditions.

Works were scheduled between 7:00 p.m. and 5:00 a.m. and included excavation, service relocations, saw cutting, vacuum excavation and truck movements. The notice identifies the activity as water main works, not the start of the main road construction package.

Service relocations have formed a substantial part of Stage 2 preparations. Council has previously listed water, sewer, gas, electricity and telecommunications works, along with stormwater upgrades and earthworks, among the early works required before the road duplication progresses. 

Four lanes and signals planned

Stage 2 covers Springfield Parkway from Topaz Road to just north of the completed Stage 1 intersection with Springfield Greenbank Arterial. It is the remaining stage of the three-part duplication program, with Stages 1 and 3 completed. 

The project will widen Springfield Parkway from two lanes to four and replace the Springfield Parkway, Topaz Road and Woodcrest Way roundabout with a signalised intersection. Plans also include road widening at Springfield College Drive and Bridgewater Road, two-metre cycle lanes in both directions and a three-metre shared path along the western side of the corridor.

Springfield Parkway carries more than 19,500 vehicles a day, according to council, and connects Springfield, Springfield Central, Camira and Goodna with business, education, health and sporting centres. Council has identified population growth as the main reason for duplicating the corridor. 

Photo Credit: City of Ispwich


Stage 2 funding retained

Council’s February announcement said the 2025–26 budget allocated $22 million to continue Stage 2 as part of $43 million over five years. The 2026–27 budget subsequently identified $22.4 million over three years to complete Stage 2; the budget material does not establish that the two figures are separate allocations that can be added together. 

Published 7-Sept-2026

Springfield Parkway Upgrade Stage 2 Moves Closer as Long-Term Road Expansion Continues

The Springfield Parkway Upgrade is set to transform one of Ipswich’s busiest transport routes, with major plans moving forward to Stage 2 to widen the key corridor linking Springfield Central with neighbouring suburbs. The project aims to improve traffic flow, reduce congestion, and support one of South East Queensland’s fastest-growing communities.



Procurement Plan Moves Project Forward

Ipswich has adopted a Significant Contracting Plan to prepare for the next stage of construction for the Springfield Parkway duplication. The adoption of this plan enables the move toward issuing tenders for Stage 2 of the project. Further details on the contracting process and project planning are available in the official announcement.

The plan is required by procurement rules before contracts of significant value or duration can be awarded. 

Project planning information also indicates that $22 million has been allocated in the 2025–2026 budget to continue Stage 2 works, as part of a broader $43 million investment spread over five years to deliver the upgrade.

The upgrade is part of a long-term strategy to duplicate Springfield Parkway and Springfield Greenbank Arterial into four-lane roads to better handle increasing traffic demand. 

Photo Credit: IpswichCC

Supporting Rapid Population Growth

Planning materials show Springfield is experiencing strong population growth, placing increased demand on local transport networks. The duplication project is designed to increase capacity along the corridor, which currently services tens of thousands of commuters each day.

Council information states that preliminary works, such as relocating underground services and constructing retaining walls, are expected to support the main construction phase. The improvements are also intended to enhance road safety and reduce travel delays for motorists, pedestrians and cyclists using the corridor.

Long-Term Planning Linked to Regional Development

The upgrade is being delivered as part of wider infrastructure planning across Springfield and surrounding areas. Local infrastructure upgrades are considered essential to support residential expansion, business development, and access to community facilities across the region.



The road network improvements are also expected to support future regional events and large-scale activities by improving access to key community venues.

Published 4-Feb-2026